ACV delivers reliable hot water at historic George & Pilgrims’ Inn

Dating back to the late 15th century, The George & Pilgrims’ Inn in Glastonbury, Somerset is a three-storey Grade 1 listed building. With 14 bedrooms alongside a busy bar and restaurant, the Inn requires a reliable heating and hot water system capable of meeting the demands of guests and day-to-day operations.

Meeting the demands of a busy hospitality venue

The Inn’s existing heating and hot water system had developed a number of faults, including leaks, with issues affecting pressure, heat distribution and water flow. These problems were impacting the system’s ability to meet demand, particularly during busy periods, while also increasing maintenance requirements.

With the additional challenge of working within a Grade 1 listed building, the replacement system needed to provide reliable modern performance while protecting the historic fabric of the property.

 

High-performance hot water from ACV

To address these challenges, Tom Oldham, Director of We Heat South, worked closely with Damon George, ACV Business Development Manager, to design and install a new heating and hot water system that would meet the Inn’s requirements while avoiding invasive alterations to the building. 

At the heart of the hot water solution are two ACV SL320 cylinders, selected for their tank-in-tank design, high storage capacity and fast recovery rates. Together, they provide a consistent supply of hot water across the Inn’s guest rooms and restaurant, including during periods of high demand. 

The cylinders were installed alongside an Ideal Commercial Heating Evomax 2 150kW wall-mounted boiler, selected to provide consistent heat generation across the building. 

Tom Oldham explains:

“ACV SL320 Cylinders are our first choice for high demand jobs such as hotels as their capacity and rapid recovery rates cope exceptionally well with busy sites.”

 

Overcoming the challenges of a historic building

The project also identified sections of undersized existing pipework that were restricting flow and contributing to pressure issues. Targeted upgrades were therefore made, including selectively introducing new pipework alongside upgraded pumps and a new control panel, with careful consideration given to the building’s listed status throughout. 

 

A reliable system with minimal disruption

The new equipment was installed within a purpose-built plantroom in The George & Pilgrims’ Inn beer garden. Locating the new plant externally helped avoid intrusion into the historic building and preserve its architectural integrity.

The project was completed within two weeks, with minimal disruption to staff and guests. The Inn now benefits from a reliable and efficient heating and hot water system capable of consistently meeting demand. 

Reflecting on his experience working with ACV, Tom Oldham adds:

“We’ve worked with ACV for several years now and have always found the customer service team to be incredibly responsive and easy to work with. The Business Development Manager is always very helpful, and in our opinion, they can’t be beaten on product quality.” 

 

Read our full case study here

 

Talk to ACV

If you’re looking for a reliable hot water solution for a hotel, hospitality venue or other high-demand commercial applications, talk to the ACV team about your project.

01383 820100
uk.sales@acv.com